Dear All,
we have assigned Inspection type 01 in material master for the inspection lots for the GRN Inspection.
Also, we have assigned Sample Drawing Procedure at inspection plan header as per below detail,
To Partial sample no | Factor per sample size | Primary | Pooled | Reserve |
---|---|---|---|---|
001 | 1 | 1 | 0 | 0 |
002 | 1 | 1 | 0 | 0 |
003 | 1 | 1 | 0 | 0 |
004 | 1 | 1 | 0 | 0 |
005 | 1 | 1 | 0 | 0 |
we have implemented the maximum sample quantity for the physical sample creation.
Please find the below To partial sample no assigned in inspection plan with Operation no.
Operation | To partial sample no | Sample Qty |
---|---|---|
0010 | 001 | 200 PCE |
0020 | 002 | 1 PCE |
0030 | 003 | 1 PCE |
Physical sample created with 200 PCE quantity only. other two samples for operation 0020 and 0030 not created.
what is the reason for other two samples was not created ?
please provide your inputs.