Hi Faizan
There are few steps to check ur EVM :
1. Ensure default method or assigned method of each object
2. Maintain consistency for EV basis and data >> if you decide to use Annual Cost Plan in your EV version then make sure each object (WBS,Actvity) has annual cost plan value.
3. To ensure POC is calculated, check schedule within activity and related settings
3. Check all parameters through SE38 program CHECKREPORT_PROGRESSANALYSIS
4. Running CNE1
5. Show EV project with PS Profile SAPPS_EV0001
note :
+ EV Basis Budget only work in WBS
+ for Internal activity :
+ Plan method : Cost Proportion and Milestone
+ Actual method : Work and Milestone
Below is screenshot of my example
salam hangat,
danniel