Hi people,
Could you give us a suggestion? Or tell us if there is some procedure to reesctructure the folow?
We have a sequence of Assessment Cycles in KEU3.
One Cycle send to another one.
The people had do reverse that but they have done in a different sequence that were executed.
It means for exemple:
They executed Cycle 1 that send to Cycle 2 that send to Cycle 3
When they reversed, they make that wrong. They reverse only the Cycle 2 without reverse the other ones and go on.
So, at this moment, when they try to execute the Cycle one again, the system doesn´t make the assessment.
It still having a balance, a value to be distributed.
Do you know if there is some transaction to reestructure the cycle 2 to be possible to make the assessment?
Thanks!
RG.